VALVE CHANGE SYSTEM
Valve change unit is an on-line equipment used to remove or replace the valve of LPG cylinder by unscrewing or screwing operation at a set torque and speed controlled by VFD.
DEGASSING UNIT
Degassing unit is an on-line equipment used to remove LPG vapour from a batch of damaged cylinders identified during post fill inspection using water and air.
HYDRO PRESSURE TEST UNIT
The function of this unit is to test the withholding capacity of 5 year testing due cylinders filled with water and at 25kg pressure. Cylinders passing this test will only proceed for repaiting and then for bottling, rest will be deemed not suitable for bottling. This system comes in 6 and 10 heads both online and offline mode and controlled by PLC.
PAINTING BOOTH
Water curtain paintbooth made out of MS structure for repainting the LPG cylinders. This comes with a blower and exhaust.
PNEUMATC PRESSURE TESTING UNIT
Pre Filling Unit
Pre filling unit is an on-line equipment used to fill 5KG/47.5 & 425 kg jumbo cylinder by time based cut off. The system shall be located before fine filling unit. A pre determined quantity of LPG is filled in the cylinder and it will helps to reduce the time required for fine filling operation on weighing scale. The quantity of LPG filled depends on the duration of operation, which can be adjusted by pneumatic timer device provided.
Fine Filling Unit
Fine filling unit is an on-line equipment used for fine filling the 19/14.2/47.5/425kg cylinder by weight based cut off. The system shall be located after pre filling unit on weighing scale.
Dip type Test bath
This system consist of a bath filled with water where in the cylinder is dipped inside the bath using pneumatic cylinders. This is used to identify any body leaks in 5kg ,47.5 kg cylinders
OVERHEAD CONVEOR
Conveyor mounted above the ground level for handling cylinders from one shed to another at different heights.